Work Profile Report [83W1]

Closed Work राष्ट्रीय राजमार्ग संख्या 87 विस्तार (नया-109) के किमी0 55.55 से किमी0 89.00 में सुदृढ़ीकरण का कार्य
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : RO/UK/12014/80/Annual Plan/2019-20 Date 24-12-2019

TS Amount (lakhs) : 4076.69 Lacs

Budget Financial Head : Not Available

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

4076.69

Resanction Cost :

4076.69

Tentative Cost :

4076.69

Exp. Upto Last Fy :

2,348.80

For CFY 2024-2025

Remaining :

1,727.89

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

2,348.80

Work completed

Sanction on : 4 years 11 months ago

24 Dec 2019

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

100 %

Tentative Completion date on : 3 years 7 hours ago

27 Nov 2021

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
33.45
33.45
33.45
-

Remark

view all

Work completed. -- as on 31-Mar-2022

Rating : 100

No Forest Case in The Work

Hindrance / Bottleneck :

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1 Road 2

Bridges on The Basis of AI: