Work Profile Report [83W13]

आई0आर0क्यू0पी0 के अन्तर्गत राष्ट्रीय राजमार्ग संख्या 87 विस्तार (नया-109) के किमी0 120.00 से किमी0 149.00 में सुदृढ़ीकरण का कार्य
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : RO/UK/Annual Plan/2021-22/Ranikhet-01 Dt. 03-03-2022

TS Amount (lakhs) : 3614 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

3614.00

Resanction Cost :

3614.00

Tentative Cost :

3614.00

Exp. Upto Last Fy :

985.57

For CFY 2024-2025

Remaining :

2,628.43

Demand :

550.00

Allotment :

597.86

Exp in CFY :

597.86

Total Up to Date Exp :

1,583.43

Construction Started

Sanction on : 2 years 9 months ago

03 Mar 2022

Physical Progress:

At start of FY 2024-2025 :

45 %

Up to Date :

75 %

Tentative Completion date on : 1 year 2 months ago

05 Oct 2023

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
29
29
0.000
29
8.000
0.000

Remark

view all

02 मी0 स्पान के 65 नं0 बाॅक्स कल्वर्ट के सापेक्ष 65 नं0 बाॅक्स कल्वर्ट पूरे भाग में पूर्ण एवं कुल डी0बी0एम0 29.00 किमी0 के सापेक्ष 24.00 किमी0 एवं बी0सी0 29.00 किमी0 के सापेक्ष 4.70 किमी0 पूर्ण, पैरापिट 1015 नं0 के सापेक्ष 850 नं0 पूर्ण, क्रैश बैरियर 1840 रनिंग मी0 के सापेक्ष 1840 रनिंग मी0 पूर्ण, के0सी0 ड्रेन 4680 रनिंग मी0 के सापेक्ष 4500 रनिंग मी0 पूर्ण। शेष कार्य प्रगति पर। -- as on 03-Dec-2024

Rating : 75

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: