Administrative Approval Detail : RO/UK/NH-309A/Ranikhet/2021-22PKG-4(C.no. 206975) Dt. 31-03-2022 (Job No- NH-309A/AP/UK/2021-22/613)
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47223.00
Resanction Cost :
47223.00
Tentative Cost :
47223.00
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
47,223.00
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 3 years 3 months ago
31 Mar 2022
Physical Progress:
At start of FY 2025-2026 :
13 %
Up to Date :
26 %
Tentative Completion date on : 1 year 7 months from now
26 Feb 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान 32.00 के सापेक्ष 16 किमी0 में पूर्ण, 8 00 मी0 दीवार निर्माण, 125 बॉक्स कल्वर्ट का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 04-Jul-2025