Work Profile Report [83W18]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : RO/UK/Annual Plan/2022-23/Ranikhet/01 (C. No. 212888) Dt. 30-03-2023 (Job No.RO/UK/AP/NH-87(Ext) (New 109)/2022-23/660)
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
212.00
Resanction Cost :
212.00
Tentative Cost :
212.00
Exp. Upto Last Fy :
34.70
For CFY 2024-2025
Remaining :
177.30
Demand :
80.00
Allotment :
35.44
Exp in CFY :
35.44
Total Up to Date Exp :
70.14
Construction Started
Sanction on : 1 year 8 months ago
30 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
47 %
Up to Date :
100 %
Tentative Completion date on : 7 months 1 week ago
14 May 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 24-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand