Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.688 | 0.688 | 0.322 | 0.366 | 0.366 | 0.000 |
83W18 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : RO/UK/Annual Plan/2022-23/Ranikhet/01 (C. No. 212888) Dt. 30-03-2023 (Job No.RO/UK/AP/NH-87(Ext) (New 109)/2022-23/660)
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 212.00 Lacs
Resanction Cost : 212.00 Lacs
Exp. Upto Last Fy : 34.70 Lacs
For CFY 2024-2025
Remaining : 177.30 Lacs
Demand : 80.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 34.70 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 47 %
Up to Date : 47 %
Sanction on :
1 year 1 month ago
30 Mar 2023
Tentative Completion date:
5 days 2 hours ago
14 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 01-Dec-2023
Physical Peramenters