Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.688 | 0.688 | 0.322 | 0.366 | 0.366 | 0.078 |
83W18 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : RO/UK/Annual Plan/2022-23/Ranikhet/01 (C. No. 212888) Dt. 30-03-2023 (Job No.RO/UK/AP/NH-87(Ext) (New 109)/2022-23/660)
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
212.00
Resanction Cost :
212.00
Tentative Cost :
212.00
Exp. Upto Last Fy : 34.70
For CFY 2024-2025
Remaining : 177.30
Demand : 80.00
Allotment : 35.44
Exp in CFY : 35.44
Total Up to Date Exp : 70.14
Construction Started
Physical Progress:
At start of FY 2024-2025 : 47 %
Up to Date : 65 %
Sanction on :
1 year 3 months ago
30 Mar 2023
Tentative Completion date:
2 months 3 days ago
14 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कुल 688 रनिंग मी0 दीवार के सापेक्ष 400 रनिंग मी0 दीवार निर्माण का कार्य पूर्ण, कल्वर्ट 1 नं0 के सापेक्ष 1 नं0 पूर्ण, पैरापिट 92 नं0 के सापेक्ष 37 नं0 पूर्ण एवं एच0 रेलिंग 36 नं0 के सापेक्ष 15 नं0 पूर्ण शेष कार्य प्रगति पर। -- as on 29-Jun-2024
Physical Peramenters