Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 2.000 | 0.000 |
83W19 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : RO/UK/Annual Plan/2023-24/Ranikhet/01 (C. No. 232287) Dt. 16-01-2024 (Job No.RO/UK/AP/NH-New 309A/2023-24/676)
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
519.24
Resanction Cost :
519.24
Tentative Cost :
519.24
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 519.24
Demand : 300.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
6 months 1 day ago
16 Jan 2024
Tentative Completion date:
10 months 3 weeks from now
11 Jun 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
निविदाओं का निस्तारण कर दिया गया है। दिनांक 14.05.2024 को LOA जारी कर दी गई है। अनुबन्ध गठित कार्य प्रगति पर। -- as on 29-Jun-2024