Work Profile Report [83W8]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : RO/UK/12014/117/Annual Plan/2019-20 Date 31-03-2020
TS Amount (lakhs) : 438.4 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
438.40
Resanction Cost :
438.40
Tentative Cost :
438.40
Exp. Upto Last Fy :
328.91
For CFY 2024-2025
Remaining :
109.49
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
328.91
Work completed
Sanction on : 4 years 8 months ago
31 Mar 2020
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 3 years 7 months ago
28 Apr 2021
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work completed. -- as on 02-Aug-2021
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Khanigad Steel Girder Bridge