Work Profile Report [8W10]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1754/।।।-2/05-64(प्रा॰आ॰)/2005 दि॰ 10.11.05 एवं 3242/।।।(2) दि॰ 14.09.12
TS Amount (lakhs) : 605.36 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
441.50
Resanction Cost :
1094.25
Tentative Cost :
1094.25
Exp. Upto Last Fy :
826.28
For CFY 2024-2025
Remaining :
267.97
Demand :
146.52
Allotment :
177.03
Exp in CFY :
146.52
Total Up to Date Exp :
972.80
Construction Started
Sanction on : 19 years 1 week ago
10 Nov 2005
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
75 %
Tentative Completion date on : 7 months 6 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 25-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand