Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.3 | 2.3 | 2.3 | 0 |
8W100 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1308(ए)/।।।(2)/19-04(एम0एम0ए0)/2017 टी.सी. ।। दि॰ 08.03.2019
TS Amount (lakhs) : 96.06 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
96.06
Resanction Cost :
96.06
Tentative Cost :
96.06
Exp. Upto Last Fy : 69.08
For CFY 2024-2025
Remaining : 26.98
Demand : 15.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 69.08
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
5 years 4 months ago
08 Mar 2019
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1. माह जनवरी 2023 में नगर पालिका क्षे़त्र जोशीमठ में हुये भूस्खलन के कारण कार्यस्थल पर कार्य बाधित रहा।
2. 2.05 किमी0 में पी0 सी0 का कार्य पूर्ण,शेष 0.250 किमी0 लम्बाई में मार्ग जोशीमठ क्षेत्र में आयी आपदा से भूस्खलित होने के कारण पी0 सी0 कार्य हेतु अनुपयुक्त है। अतः उक्त लम्बाई में पी0 सी0 कार्य किया जाना सम्भव नहीं है।
-- as on 05-Apr-2024
Physical Peramenters