Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6 | 0 |
8W111 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1220/।।।(2)/19-04(एम0एल0ए0)/2017 टीसी दि0 05.03.2019
TS Amount (lakhs) : 290.63 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
352.51
Resanction Cost :
373.87
Tentative Cost :
352.51
Saving
21.36
Exp. Upto Last Fy : 356.82
For CFY 2024-2025
Remaining : 17.05
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 356.82
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
05 Mar 2019
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। वर्तमान में डी0 एल0 पी0 अवधि में है। -- as on 07-Jun-2024
Physical Peramenters