Work Profile Report [8W136]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 3976/।।।(2)/17-04(एम0एल0ए0)/2017टी0सी0 दि॰ 12.112.107
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
9.10
Resanction Cost :
9.10
Tentative Cost :
8.50
Saving
0.60
Exp. Upto Last Fy :
8.50
For CFY 2025-2026
Remaining :
0.60
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
8.50
Work deferred
Sanction on : 7 years 6 months ago
12 Dec 2017
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 8 months 3 days ago
31 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
निरस्तीकरण प्रस्ताव गठित किया जाना हैै। -- as on 25-Mar-2025
Assets :
Work not linked with IM