Work Profile Report [8W14]

सुराईथोटा के 2 किमी॰ आगे से पगरासू तक मोटर मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities
  • alerts

  • Documents
  • Samples

Administrative Approval Detail : 1754/।।।-2/05-64(प्रा॰आ॰)/2005 दि॰ 10.11.05

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : TSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

206.40

Resanction Cost :

206.40

Tentative Cost :

206.40

Exp. Upto Last Fy :

29.06

For CFY 2025-2026

Remaining :

177.34

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

29.06

Work deferred

Sanction on : 19 years 7 months ago

10 Nov 2005

Physical Progress:

At start of FY 2025-2026 :

30 %

Up to Date :

30 %

Tentative Completion date on : 3 months 3 days ago

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
4
4
4
-
Bridge
1 (70m)
1 (70m)
1 (70m)
-

Remark

view all

Additional NPV paid on 04.04.2024.इस कार्याल्य के पंत्राक 2244 /अनु दिनांक 10.09.2024 द्वारा . भू-वैज्ञानिक कार्यालय मुख्य अभियन्ता-। लोक निमाण विभाग पौड़ी को दिनांक 28.09.2024 एवं 29.9.2024 को संयुक्त निरीक्षण हेतु पत्र प्रेषित किया गया है। -- as on 11-Sep-2024

Rating : 30

Forest Case Pending At : 13: AIP DFO

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI: