Work Profile Report [8W148]

अनुसूया गेट से मण्डल के ढुमकला तोक में बालखिला नदी पर 18 मी0 स्पान लौह सेतु का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

  • Project Activities
  • alerts

  • Documents
  • Samples

Administrative Approval Detail : 331/।।।(2)/15-24 (प्रा0आ0)/2014 दि॰ 14.01.2015

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Bridges State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

0.72

Resanction Cost :

0.72

Tentative Cost :

0.72

Exp. Upto Last Fy :

0.35

For CFY 2025-2026

Remaining :

0.37

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.35

Work deferred

Sanction on : 10 years 5 months ago

14 Jan 2015

Physical Progress:

At start of FY 2025-2026 :

5 %

Up to Date :

5 %

Tentative Completion date on : 3 months 3 days ago

31 Mar 2025

Actual Completion Date : 5 years 3 months ago

01 Apr 2020

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Bridge
1 (18m)
1 (18m)
1 (18m)
-

Remark

view all

सेतु निर्माण पर स्थल चयन पर ग्रामीणों का विवाद -- as on 09-Nov-2024

Rating : 49

No Forest Case in The Work

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI: