Work Profile Report [8W16]

लाता- लाता मन्दिर मोटर मार्ग के किमी॰ 0.50 से 4.00 तक विस्तार
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 1754/।।।-2/05-64(प्रा॰आ॰)/2005 दि॰ 10.11.05 एवं पुन0स्वी0 4178/।।।-2/17-04(एम.एल.ए.)/2017 दि॰ 27.12.2017

TS Amount (lakhs) : 69.64 Lacs

Budget Financial Head : TSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

50.40

Resanction Cost :

92.81

Tentative Cost :

92.81

Exp. Upto Last Fy :

73.98

For CFY 2025-2026

Remaining :

18.83

Demand :

18.83

Allotment :

20.05

Exp in CFY :

0.00

Total Up to Date Exp :

73.98

Construction Started

Sanction on : 7 years 3 months ago

27 Dec 2017

Physical Progress:

At start of FY 2025-2026 :

76 %

Up to Date :

57 %

Tentative Completion date on : 4 weeks 1 day from now

06 May 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3.5
1.5
1.5
-

Remark

view all

Tender for remaining work in progress. -- as on 25-Jul-2024

Rating : 82

Forest Case Pending At : 15: AIP Nodal

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: