Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6 | 0 |
8W161 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 7075/।।।(2)/13-41 (प्रा0आ0)/2013 दि॰ 20.12.2013
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
106.38
Resanction Cost :
106.38
Tentative Cost :
106.38
Exp. Upto Last Fy : 31.63
For CFY 2024-2025
Remaining : 74.75
Demand : 15.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 31.63
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
10 years 6 months ago
20 Dec 2013
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
उत्तराखण्ड शासन के प0 946/4- 16 /1(124)/2016 दि0 16.09.2016 द्वारा सैद्धान्तिक स्वीकृति प्राप्त। कार्य के द्वितीय चरण की स्वीकृति प्राप्त, जिसके सपेक्ष कार्य पूर्ण।
इस कार्यालय के पत्रांक 1419/23 एल.ए. दि॰ 28.07.2021, प0 283/24 एल.ए. दि॰ 25.02.2022 द्वारा पुनः अनुपालन आख्या डी॰एफ॰ओ॰ केदारनाथ को प्रेषित। पुनः डी॰एफ॰ओ॰ केदारनाथ द्वारा सूचित एन॰पी॰वी॰ की संशोधित धनराशि रू॰ 1791400.00 को वन विभाग के पक्ष में दिनांक माह 20/06/2023 को भुगतान कर दिया गया है। अतिथि तक विधिवत स्वीकृति अपेक्षित है |
-- as on 30-Dec-2023
Physical Peramenters