Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
8W163 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 511/111(2)/18-04(एम0एल0ए0) /2017 दि॰ 09.02.18
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.12
Resanction Cost :
37.12
Tentative Cost :
37.12
Exp. Upto Last Fy : 2.68
For CFY 2024-2025
Remaining : 34.44
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.68
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
6 years 5 months ago
09 Feb 2018
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
संरेखण प्रस्ताव अनुमोदित। क्षतिपूरक वृक्षारोपण स्थल हेतु सिविल भूमि उपलब्ध कराये जाने हेतु इस कार्यालय के पत्रांक 366/23 एल. ए. दि0 16.02.2024 द्वारा उपजिलाधिकारी चमोली को पत्र प्रेषित। -- as on 04-Apr-2024
Physical Peramenters