Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.5 | 0 |
8W168 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 333/।।।(2)/14-46 (प्रा0आ0)/2013 दि॰ 21.01.2014
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
44.33
Resanction Cost :
44.33
Tentative Cost :
44.33
Exp. Upto Last Fy : 39.47
For CFY 2024-2025
Remaining : 4.86
Demand : 0.63
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 39.47
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
10 years 5 months ago
21 Jan 2014
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
अपर सचिव, उत्तराखण्ड शासन के प0 100/(30)/2016 दि॰ 11.06.2018 द्वारा 0.77 हे0 वनभूमि की विधिवत स्वीकृति एवं द्वितीय चरण की स्वीकृति प्राप्त।
डी॰एफ॰ओ॰, केदारनाथ के प॰ 355/9-1(3) दि॰ 18.07.19 द्वारा वृक्षों के पातन हेतु प्रभागीय लौंगिंग प्रबन्धक, उत्तराखण्ड वन विकास निगम, कर्णप्रयाग को पत्र लिखा गया है। fजसके क्रम में उनके प॰ 513/लेखा जनरल fद॰ 07.08.19 द्वारा अवगत करायी गयी लौट की धनराfश लौट की धनराfश रु॰ 69856.00 मात्र का भुगतान डी॰डी॰ नं॰ 023043 fद॰ 18.11.19 द्वारा कर fदया गया है। मार्ग से प्रभावित अवशेष कास्तकारों को उनकी नापभूमि प्रतिकर के भुगतान हेतु पुनरीक्षित प्रस्ताव गठित किया जा रहा है।
प्रस्ताव सं॰ एफपी/यूके/रोड/10736/2015
-- as on 04-Apr-2024
Physical Peramenters