Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
8W170 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5150/।।।(2)/10-18 (प्रा0आ0)/2010
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.80
Resanction Cost :
37.80
Tentative Cost :
37.80
Exp. Upto Last Fy : 10.75
For CFY 2024-2025
Remaining : 27.05
Demand : 25.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 10.75
Work completed
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
13 years 11 months ago
16 Aug 2010
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
0.91 हे0 वनभूमि की विधिवत स्वीकृति भारत सरकार के पत्रांक 8बी/यू.सी.पी./06/56/2016/ एफ.सी./96 दि0 28.09.2021 द्वारा प्राप्त। रु0 80.83 लाख केे द्वितीय चरण स्टैज-1 की स्वीकृति प्राप्त। उक्त कार्य मा0मु0मं.घो0 सं0 58/2022 दि0 07.12.2021 से आच्छादित हैं। -- as on 02-Sep-2023
Physical Peramenters