Work Profile Report [8W176]
Tenders
Aggrements
alerts
Samples
Administrative Approval Detail : 5150/।।।(2)/10-18 (प्रा0आ0)/2010 दि0 16.08.2010
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
100.80
Resanction Cost :
100.80
Tentative Cost :
100.80
Exp. Upto Last Fy :
100.78
For CFY 2025-2026
Remaining :
0.02
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
100.78
Work completed
Sanction on : 14 years 10 months ago
16 Aug 2010
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
100 %
Tentative Completion date on : 9 months 4 days ago
30 Sep 2024
Actual Completion Date : 3 months 3 days ago
31 Mar 2025
Physical Linear Components
Remark
कार्य के द्वितीय चरण की स्वीकृति प्राप्त। जिसके सापेक्ष कार्य पूर्ण। अवशेष धनराशि से मुआवजा भुगतान किया जना है। -- as on 24-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: