Work Profile Report [8W176]
Tenders
Aggrements
alerts
Samples
Administrative Approval Detail : 5150/।।।(2)/10-18 (प्रा0आ0)/2010 दि0 16.08.2010
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
100.80
Resanction Cost :
100.80
Tentative Cost :
100.80
Exp. Upto Last Fy :
96.93
For CFY 2024-2025
Remaining :
3.87
Demand :
3.87
Allotment :
0.79
Exp in CFY :
0.79
Total Up to Date Exp :
97.72
Alignment Approved
Sanction on : 14 years 4 months ago
16 Aug 2010
Physical Progress:
At start of FY 2024-2025 :
95 %
Up to Date :
95 %
Tentative Completion date on : 2 months 3 weeks ago
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य के द्वितीय चरण की स्वीकृति प्राप्त। जिसके सापेक्ष कार्य पूर्ण। अवशेष धनराशि से मुआवजा भुगतान किया जना है। -- as on 24-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand