Work Profile Report [8W189]

माननीय मुख्यमंत्री घोषणान्तर्गत वर्ष 2015 में चमोली-लासी-सरतोली मोटर मार्ग का बैरासकुण्ड तक विस्तारीकरण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0 2599/।।।(2)/16-05 (एम.एल.ए.)/2015 दि0 10.10.2016

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

184.52

Resanction Cost :

15.00

Tentative Cost :

15.00

Exp. Upto Last Fy :

3.68

For CFY 2025-2026

Remaining :

11.32

Demand :

10.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

3.68

Survey work done

Sanction on : 9 years 1 month ago

10 Oct 2016

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

10 %

Tentative Completion date on : 1 year 3 months from now

31 Mar 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
20
20
20
-
Bridge
1 (36m)
1 (36m)
1 (36m)
-

Remark

view all

Overall Saving 169.52 has been recorded as expected cost of work reduced from 184.52 to 15.00 . -- as on 07-Dec-2025

Rating : 2

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: