Work Profile Report [8W189]

माननीय मुख्यमंत्री घोषणान्तर्गत वर्ष 2015 में चमोली-लासी-सरतोली मोटर मार्ग का बैरासकुण्ड तक विस्तारीकरण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

  • Aggrements
  • Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0 2599/।।।(2)/16-05 (एम.एल.ए.)/2015 दि0 10.10.2016

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

184.52

Resanction Cost :

184.52

Tentative Cost :

184.52

Exp. Upto Last Fy :

3.68

For CFY 2025-2026

Remaining :

180.84

Demand :

10.00

Allotment :

3.30

Exp in CFY :

0.00

Total Up to Date Exp :

3.68

Survey work done

Sanction on : 8 years 5 months ago

10 Oct 2016

Physical Progress:

At start of FY 2025-2026 :

0 %

Up to Date :

0 %

Tentative Completion date on : 6 days 52 minutes ago

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
20
20
20
-
Bridge
1 (36m)
1 (36m)
1 (36m)
-

Remark

view all

सर्वेक्षण कार्य के दौरान ग्राम सरतेाती के ग्रामीणों द्वारा विवाद किया जा रहा है। विवाद सुलझाने का प्रयास किया जा रहा है। -- as on 31-Jul-2020

Rating : 2

No Forest Case in The Work

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI: