Work Profile Report [8W207]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 3257/।।।(2)ध्16-54(प्रा0आ0)/2016 दि0 29.12.2016
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2.70
Resanction Cost :
2.70
Tentative Cost :
2.70
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
2.60
Demand :
2.00
Allotment :
2.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Survey work done
Sanction on : 7 years 10 months ago
29 Dec 2016
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Survey work done. -- as on 10-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand