Administrative Approval Detail : शा0सं0 611/।।।(2)/21-04(एम.एल.ए.)/2017 टीसी दि0 19.03.2021
TS Amount (lakhs) : 17.1 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
17.10
Resanction Cost :
17.10
Tentative Cost :
17.10
Exp. Upto Last Fy :
11.14
For CFY 2025-2026
Remaining :
5.96
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
11.14
Survey work done
Sanction on : 4 years 3 months ago
19 Mar 2021
Physical Progress:
At start of FY 2025-2026 :
30 %
Up to Date :
30 %
Tentative Completion date on : 4 days 18 hours ago
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य ई-डी0पी0आर0, (आई0डी0 2780) लागत रु0 435.65 लाख, स्पान 80 मी0 आगणन दि0 08.05.2025 को स्वीकृति हेतु प्रेषित। -- as on 03-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand