Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.125 | 3.7 | 0.000 | 3.7 | 0.000 | 0.000 |
8W282 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1948 ;1द्धध्21.04 ध्2017 ;एम.एल.ए.द्धध्2017 दि0 02.07.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
141.22
Resanction Cost :
141.22
Tentative Cost :
141.22
Exp. Upto Last Fy : 133.67
For CFY 2024-2025
Remaining : 7.55
Demand : 4.50
Allotment : 2.50
Exp in CFY : 2.50
Total Up to Date Exp : 136.16
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 2 weeks ago
02 Jul 2021
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
वास्तविक 3.70 किमी0 लम्बाई में पहाड़ कटान कार्य पूर्ण। -- as on 20-Apr-2023
Physical Peramenters