Work Profile Report [8W302]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : GO No- 426(1)/III(2)/22-04(M.L.A.)/2017 TCI
TS Amount (lakhs) : 124.1 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
124.10
Resanction Cost :
132.15
Tentative Cost :
122.93
Saving
9.22
Exp. Upto Last Fy :
113.51
For CFY 2024-2025
Remaining :
18.64
Demand :
3.90
Allotment :
3.36
Exp in CFY :
3.19
Total Up to Date Exp :
116.70
In Maintenance After Completion
Sanction on : 2 years 11 months ago
05 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 9 months ago
24 Mar 2023
Actual Completion Date : 1 year 2 weeks ago
06 Dec 2023
Physical Linear Components
Remark
Overall Saving 9.22 has been recorded as expected cost of work reduced from 132.15 to 122.93 . मुख्य अभियन्ता, लो0नि0वि0, पौड़ी के पत्रांक 5142/73 नाबार्ड (7-1)-पौड़ी/2021 दिनांक 23.09.2024 द्वारा पांच वर्षों के अनुरक्षण का आगणन, लागत रु0 0.47 लाख स्वीकृति हेतु प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, देहरादून को प्रेषित। इस कार्यालय के प0 2541/नाबार्ड दि0 13.11.2024 द्वारा पी0सी0आर0 अधीक्षण अभियन्ता, गोपेश्वर को प्रेषित। -- as on 30-Nov-2024