Work Profile Report [8W308]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : मुख्य विकास अधिकारी चमोली के पत्रांक 611/जि0 यो0/2021-22 दि0 29.08.2022
TS Amount (lakhs) : 9.62 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
9.62
Resanction Cost :
9.62
Tentative Cost :
9.62
Exp. Upto Last Fy :
9.61
For CFY 2025-2026
Remaining :
0.01
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
9.61
Work completed
Sanction on : 2 years 10 months ago
29 Aug 2022
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 3 months ago
31 Mar 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 11-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: