Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1 | 0 |
8W364 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई-फाईल सं॰ 33442/लो0नि0अनु0-2 दि॰ 14.09.2022
TS Amount (lakhs) : 77.68 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
77.68
Resanction Cost :
77.68
Tentative Cost :
77.68
Exp. Upto Last Fy : 65.93
For CFY 2024-2025
Remaining : 11.75
Demand : 11.75
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 65.93
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 10 months ago
14 Sep 2022
Tentative Completion date:
1 year 1 week ago
09 Jul 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 05-Apr-2024
Physical Peramenters