Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 2.8 | 2.8 | 0 |
8W39 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1956/।।।(2)/20-04(एम.एल.ए.)/2017 टी.सी.। दि0 23.10.2020
TS Amount (lakhs) : 363.61 Lacs
Financial Detail
Sanction Cost : 204.17 Lacs
Resanction Cost : 217.95 Lacs
Exp. Upto Last Fy : 201.78 Lacs
For CFY 2024-2025
Remaining : 16.17 Lacs
Demand : 2.38 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 201.78 Lacs
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 6 months ago
23 Oct 2020
Tentative Completion date:
7 months 2 weeks ago
30 Sep 2023
Actual Completion Date:
7 months 2 weeks ago
30 Sep 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 06-Mar-2024
Physical Peramenters