Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 2.8 | 2.8 | 0 |
8W39 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1956/।।।(2)/20-04(एम.एल.ए.)/2017 टी.सी.। दि0 23.10.2020
TS Amount (lakhs) : 363.61 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
204.17
Resanction Cost :
217.95
Tentative Cost :
217.95
Exp. Upto Last Fy : 201.78
For CFY 2024-2025
Remaining : 16.17
Demand : 5.44
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 201.78
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 8 months ago
23 Oct 2020
Tentative Completion date:
9 months 2 weeks ago
30 Sep 2023
Actual Completion Date:
1 year 3 months ago
31 Mar 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। वर्तमान में डी0 एल0 पी0 अवधि में है। -- as on 07-Jun-2024
Physical Peramenters