Work Profile Report [8W391]
Tenders
alerts
Documents
Samples
Administrative Approval Detail : शा0 ई0 फाइल सं0. 36696 लो0नि0 अनुभाग-2 दि0 11.05.2023
TS Amount (lakhs) : 235.38 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
235.38
Resanction Cost :
235.38
Tentative Cost :
235.38
Exp. Upto Last Fy :
218.27
For CFY 2025-2026
Remaining :
17.11
Demand :
17.00
Allotment :
75.72
Exp in CFY :
0.00
Total Up to Date Exp :
218.27
Construction Started
Sanction on : 1 year 10 months ago
11 May 2023
Physical Progress:
At start of FY 2025-2026 :
74 %
Up to Date :
95 %
Tentative Completion date on : 1 month 4 days from now
10 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड कटान पूर्ण। शेष लम्बाई में कार्य प्रगति में है। -- as on 25-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: