Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
8W391 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 ई0 फाइल सं0. 36696 लो0नि0 अनुभाग-2 दि0 11.05.2023
TS Amount (lakhs) : 235.38 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
235.38
Resanction Cost :
235.38
Tentative Cost :
235.38
Exp. Upto Last Fy : 142.54
For CFY 2024-2025
Remaining : 92.84
Demand : 80.00
Allotment : 35.00
Exp in CFY : 0.00
Total Up to Date Exp : 142.54
Construction Started
Physical Progress:
At start of FY 2024-2025 : 74 %
Up to Date : 74 %
Sanction on :
1 year 2 months ago
11 May 2023
Tentative Completion date:
9 months 3 weeks from now
10 May 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
4.20 किमी0 लम्बाई में पहाड कटान पूर्ण। शेष लम्बाई में कार्य प्रगति में है। -- as on 07-Jul-2024
Physical Peramenters