Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
8W391 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 ई0 फाइल सं0. 36696 लो0नि0 अनुभाग-2 दि0 11.05.2023
TS Amount (lakhs) : 235.38 Lacs
Financial Detail
Sanction Cost : 235.38 Lacs
Resanction Cost : 235.38 Lacs
Exp. Upto Last Fy : 142.54 Lacs
For CFY 2024-2025
Remaining : 92.84 Lacs
Demand : 80.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 142.54 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 74 %
Up to Date : 74 %
Sanction on :
1 year 1 week ago
11 May 2023
Tentative Completion date:
11 months 3 weeks from now
10 May 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान कार्य प्रगति पर है। -- as on 07-Jan-2024