Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 0.000 | 0.000 |
8W392 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई-फाईल सं॰ 37619 लो0नि0अनु0-2 दि॰ 19.05.2023
TS Amount (lakhs) : 55.99 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
55.99
Resanction Cost :
55.99
Tentative Cost :
55.99
Exp. Upto Last Fy : 31.70
For CFY 2024-2025
Remaining : 24.29
Demand : 24.00
Allotment : 7.35
Exp in CFY : 0.54
Total Up to Date Exp : 32.24
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
1 year 1 month ago
19 May 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान कार्य प्रगति पर है। -- as on 07-Jan-2024
Physical Peramenters