Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.25 | 2.25 | 0.000 | 2.25 | 0.000 | 0.000 |
8W393 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई-फाईल सं॰ 37399 लो0नि0अनु0-2 दि॰ 19.05.2023
TS Amount (lakhs) : 80.83 Lacs
Financial Detail
Sanction Cost : 80.83 Lacs
Resanction Cost : 80.83 Lacs
Exp. Upto Last Fy : 38.43 Lacs
For CFY 2024-2025
Remaining : 42.40 Lacs
Demand : 30.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 38.43 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 55 %
Sanction on :
1 year 23 minutes ago
19 May 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान कार्य प्रगति पर है। -- as on 20-Feb-2024
Physical Peramenters