Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15 | 15 | 15 | 0 | ||
No of Bridges | 3 | 3 | 3 | 0 |
8W435 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा सं0 164441/2023 ई फाइल सं0 35599 लोक निर्माण अनुभाग-2 दि0 26.10.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
45.77
Resanction Cost :
45.77
Tentative Cost :
45.77
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 45.77
Demand : 45.77
Allotment : 0.00
Exp in CFY : 19.51
Total Up to Date Exp : 19.51
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 15 %
Sanction on :
8 months 3 weeks ago
26 Oct 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित कार्य प्रगति पर है। -- as on 07-May-2024
Physical Peramenters