Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 23 | 23 | 23 | 0 |
8W439 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 4088/III(2) /2023-(प्रा0 आ0)/2023
TS Amount (lakhs) : 80.24 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
80.24
Resanction Cost :
80.24
Tentative Cost :
80.24
Exp. Upto Last Fy : 51.11
For CFY 2024-2025
Remaining : 29.13
Demand : 29.13
Allotment : 20.00
Exp in CFY : 0.00
Total Up to Date Exp : 51.11
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
8 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
3 months 1 week from now
29 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 14-Mar-2024
Physical Peramenters