Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11 | 11 | 0.000 | 11 | 0.000 | 0.000 |
8W443 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 5082/III(2)/2023-01(प्रा0 आ0) /2023 दि0 09.11.2023
TS Amount (lakhs) : 272.75 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
272.75
Resanction Cost :
272.75
Tentative Cost :
272.75
Exp. Upto Last Fy : 109.14
For CFY 2024-2025
Remaining : 163.61
Demand : 163.61
Allotment : 30.00
Exp in CFY : 29.58
Total Up to Date Exp : 138.73
Current Liability: 29.58
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 65 %
Sanction on :
8 months 1 week ago
09 Nov 2023
Tentative Completion date:
4 months 4 days from now
22 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 14-Mar-2024
Physical Peramenters