Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10.4 | 10.4 | 0.000 | 10.4 | 0.000 | 0.000 |
8W444 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 5082/III(2)/2023-01(प्रा0 आ0) /2023 दि0 09.11.2023
TS Amount (lakhs) : 248.3 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
248.30
Resanction Cost :
248.30
Tentative Cost :
248.30
Exp. Upto Last Fy : 0.73
For CFY 2024-2025
Remaining : 247.57
Demand : 247.57
Allotment : 140.00
Exp in CFY : 114.75
Total Up to Date Exp : 115.48
Current Liability: 112.67
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 60 %
Sanction on :
8 months 1 week ago
09 Nov 2023
Tentative Completion date:
4 months 5 days from now
23 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 11-Mar-2024
Physical Peramenters