Work Profile Report [8W444]
Tenders
Project Activities
alerts
Administrative Approval Detail : शा0 सं0 5082/III(2)/2023-01(प्रा0 आ0) /2023 दि0 09.11.2023
TS Amount (lakhs) : 248.3 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
248.30
Resanction Cost :
248.30
Tentative Cost :
248.30
Exp. Upto Last Fy :
0.73
For CFY 2024-2025
Remaining :
247.57
Demand :
247.57
Allotment :
140.00
Exp in CFY :
114.75
Total Up to Date Exp :
115.48
Current Liability:
112.67
Construction Started
Sanction on : 1 year 2 weeks ago
09 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
60 %
Tentative Completion date on : 16 hours 46 minutes ago
23 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 11-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand