Work Profile Report [8W445]
Tenders
Project Activities
alerts
Administrative Approval Detail : शा0 सं0 5082/III(2)/2023-01(प्रा0 आ0) /2023 दि0 09.11.2023
TS Amount (lakhs) : 331.66 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
331.66
Resanction Cost :
331.66
Tentative Cost :
331.66
Exp. Upto Last Fy :
310.32
For CFY 2025-2026
Remaining :
21.34
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
310.32
Current Liability:
103.80
Work completed
Sanction on : 1 year 7 months ago
09 Nov 2023
Physical Progress:
At start of FY 2025-2026 :
70 %
Up to Date :
100 %
Tentative Completion date on : 6 months 3 weeks ago
10 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण । दाायित्वों का भुगतान शेष। -- as on 01-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: