Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 0.000 | 10 | 0.000 | 0.000 |
8W445 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 5082/III(2)/2023-01(प्रा0 आ0) /2023 दि0 09.11.2023
TS Amount (lakhs) : 331.66 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
331.66
Resanction Cost :
331.66
Tentative Cost :
331.66
Exp. Upto Last Fy : 88.96
For CFY 2024-2025
Remaining : 242.70
Demand : 242.70
Allotment : 140.00
Exp in CFY : 103.96
Total Up to Date Exp : 192.92
Current Liability: 103.80
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 70 %
Sanction on :
8 months 1 week ago
09 Nov 2023
Tentative Completion date:
4 months 3 weeks from now
10 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 14-Mar-2024
Physical Peramenters