Work Profile Report [8W467]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश ई-फाईल सं॰ 64447/लो0नि0अनु0-2 दि॰ 30.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
7.90
Resanction Cost :
7.90
Tentative Cost :
7.90
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
7.90
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Work deferred
Sanction on : 1 year 7 months ago
30 Nov 2023
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 3 months 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 7.8 has been counted as tentative cost increased from 0.1 to 7.9 . -- as on 15-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: