Work Profile Report [8W500]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी चमोली का पत्रांक 2703/ तेरह- ए0सी0आर0ए0-रा0आ0मो0नि0(2023-2024) दि0 20.02.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2.25
Resanction Cost :
2.25
Tentative Cost :
2.25
Exp. Upto Last Fy :
2.24
For CFY 2025-2026
Remaining :
0.01
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.24
Work completed
Sanction on : 1 year 4 months ago
20 Feb 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 4 days ago
30 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 11-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: