Work Profile Report [8W53]

सुन्दरवन में 80 मी0 स्पान एम0एस0 वायर रोप केबिल पर इंजन आपरेटेड ट्राली का निर्माण एवं लगाने का कार्य
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

  • Project Activities
  • alerts

    Documents

    Samples

Administrative Approval Detail : 3800/।।। (2)/14-12 (प्रा॰आ॰)/2014 दि॰ 26.06.2014

TS Amount (lakhs) : 24.95 Lacs

Budget Financial Head : Bridges State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

24.95

Resanction Cost :

24.95

Tentative Cost :

14.20

Saving

10.75

Exp. Upto Last Fy :

14.20

For CFY 2025-2026

Remaining :

10.75

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

14.20

Work deferred

Sanction on : 11 years 1 week ago

26 Jun 2014

Physical Progress:

At start of FY 2025-2026 :

50 %

Up to Date :

50 %

Tentative Completion date on : 8 months 3 days ago

31 Oct 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Bridge
1 (80m)
1 (80m)
1 (80m)
-

Remark

view all

वर्तमान में ग्रामीणों द्वारा ट्राली निर्माण का विरोध किया जा रहा है। कार्य निरस्त किया जाना है। -- as on 25-Mar-2025

Rating : 57

No Forest Case in The Work

Hindrance / Bottleneck : To Cancel

Assets :

Work not linked with IM

Bridges on The Basis of AI: