Work Profile Report [8W584]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी, चमोली की ई-पत्रावली ESTO-ADSTOOTH(OTH)/48/2024-05-DISTRICT PLAN (computer No. 8692) दिनांक 04.09.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.00
Resanction Cost :
3.00
Tentative Cost :
3.00
Exp. Upto Last Fy :
2.86
For CFY 2025-2026
Remaining :
0.14
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.86
Work completed
Sanction on : 10 months 18 hours ago
04 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष। -- as on 25-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: