Work Profile Report [8W78]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : 1754/।।।-2/05-64(प्रा॰आ॰)/2005 दि॰ 10.11.05
TS Amount (lakhs) : 72 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
72.00
Resanction Cost :
50.00
Tentative Cost :
50.00
Exp. Upto Last Fy :
47.31
For CFY 2025-2026
Remaining :
2.69
Demand :
1.42
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
47.31
Current Liability:
1.27
Construction Started
Sanction on : 20 years 1 month ago
10 Nov 2005
Physical Progress:
At start of FY 2025-2026 :
45 %
Up to Date :
45 %
Tentative Completion date on : 2 weeks 1 day from now
31 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 22 has been recorded as expected cost of work reduced from 72 to 50 . -- as on 11-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand