Work Profile Report [8W78]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1754/।।।-2/05-64(प्रा॰आ॰)/2005 दि॰ 10.11.05
TS Amount (lakhs) : 72 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
72.00
Resanction Cost :
72.00
Tentative Cost :
72.00
Exp. Upto Last Fy :
45.94
For CFY 2024-2025
Remaining :
26.06
Demand :
1.37
Allotment :
1.37
Exp in CFY :
1.37
Total Up to Date Exp :
47.31
Current Liability:
1.27
Construction Started
Sanction on : 19 years 1 month ago
10 Nov 2005
Physical Progress:
At start of FY 2024-2025 :
45 %
Up to Date :
45 %
Tentative Completion date on : 1 year 6 days from now
31 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Tender called three times. Due to hard rock required progress not achieved by contractors, Hence agreements terminated. Revised estimate with alternate option to be prepared. -- as on 25-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand