Work Profile Report [8W97]

मा0मुख्यमंत्री घोषणान्तर्गत जनपद चमोली के स्थान गोविन्दघाट में पार्किग निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

  • Project Activities
  • alerts

    Documents

    Samples

Administrative Approval Detail : fजलाfधकारी, चमोली का प0 1099/तेरह-एम0बी0(2017-18) fद0 28.11.2018

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

218.78

Resanction Cost :

0.01

Tentative Cost :

0.01

Exp. Upto Last Fy :

0.00

For CFY 2025-2026

Remaining :

0.01

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Work deferred

Sanction on : 6 years 7 months ago

28 Nov 2018

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

0 %

Tentative Completion date on : 2 years 3 months ago

31 Mar 2023

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Jobs
1
1
1
-

Remark

view all

मा॰ उच्च न्यायालय नैनीताल के आदेशानुसार नदी तट से 200 मी0 की दूरी पर कोई भी निर्माण कार्य किया जाना प्रतिबन्धित है, जबकि प्रस्तावित कार्यस्थल नदी तट से मात्र 20 मी0 की दूरी पर स्थित है। जिलाधिकारी चमोली के पत्रांक 3076/तेरह-एम0बी0(17-18) दिनांक 22.02.2019 के अनुपालन में कार्य प्रारम्भ करने की अनुमति हेतु मुख्य अभियन्ता लो.नि.वि. पौड़ी के पत्रांक 1304/516 विविध-पौड़ी/2019 दिनांक 03.06.2019 एवं पत्रांक 1850/516 विविध- पौड़ी/2020 दिनांक 05.08.2020 द्वारा प्रमुख अभियन्ता एवं विभागाध्यक्ष से अनुरोध किया गया है। वर्तमान तक दिशा निर्देश अपेक्षित। -- as on 26-Mar-2025

Rating : 0

No Forest Case in The Work

Hindrance / Bottleneck : To Cancel

Assets :

Work not linked with IM

Bridges on The Basis of AI: