Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 60 | 60 | 60 | 0 |
9W172 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5927/।।।(2)/13-31(प्रा0आ0)/2013 दिं0 22.11.2013
TS Amount (lakhs) : 20.16 Lacs
Financial Detail
Sanction Cost : 29.55 Lacs
Resanction Cost : 29.55 Lacs
Exp. Upto Last Fy : 14.23 Lacs
For CFY 2024-2025
Remaining : 15.32 Lacs
Demand : 15.32 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 14.23 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 years 5 months ago
22 Nov 2013
Tentative Completion date:
3 years 6 months ago
31 Oct 2020
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 17: AIP Govt of India
Bottelneck: no issue
वन भूमि की सैद्धान्तिक स्वीकृति प्राप्त। विधिवत स्वी0 हेतु अनुपालन आख्या में नो0अधि0 देहरादून द्वारा लगाई गयी आपत्तियो का निराकरण इस कार्या0 के पत्रांक 579/ 29 एम0जी0 दिं0 06.03.21 द्वारा प्रेषित कार्य की दि्वतीय चरण की डी0पी0आर0 गठित कर मु0अभि0 लो0नि0वि0 हल्द्वानी के पत्रांक 657/10 याता-ह0/ 2020 दिं0 18.02.21 द्वारा प्रमुख अभि0 एवं विभागाध्यक्ष कार्या0 को प्रेषित। डिजाईन सैल द्वारा लगायी गयी आपत्तियो का निराकरण हेतु कन्सलट्रेन्ट को इस कार्या0 पत्रांक 1081/ 4सी दिं0 19.05.21 द्वारा पत्र प्रेषित। डी0पी0आर0 लागत रू0 714.01 लाख मात्र का गठित कर मुख्य अभियन्ता, लो0नि0वि0, हल्द्वानी के पत्रांक 3733/ 10 याता0 ह0 / 2020-21 दिं0 11.08.2021 द्वारा प्रमुख सचिव लो0नि0वि0 उत्तराखण्ड शासन देहरादून को प्रेषित। दिं0 09.09.2021 को शासन में मार्ग की स्वीकृति हेतु प्रस्तुतिकरण किया गया है। विधिवत् स्वीकृति जारी करने हेतु नोडल अधिकारी देहरादून के पत्र सं0 1341/12-1 दिनाॅक 06.01.2024 द्वारा भारत सरकार को लिखा गया हैं। -- as on 26-Apr-2024
Physical Peramenters