Work Profile Report [9W24]

एस0सी0पी0 के अन्तर्गत नैनीताल में देवीधूरा से धापला तक मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 827/।।।-(2)/06-76(प्रा0आ0)/05 दिं0 28.03.2006

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

178.00

Resanction Cost :

178.00

Tentative Cost :

178.00

Exp. Upto Last Fy :

3.08

For CFY 2024-2025

Remaining :

174.92

Demand :

0.10

Allotment :

0.10

Exp in CFY :

0.00

Total Up to Date Exp :

3.08

Alignment Approved

Sanction on : 18 years 7 months ago

28 Mar 2006

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

0 %

Tentative Completion date on : 2 years 2 months ago

31 Aug 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
10
6
6
-

Remark

view all

संमरेखन अनुमोदित। 4.00 किमी0 पी0एम0जी0एस0वाई0 द्वारा फतेहपुर नाईसेला बेल बसानी मोटर मार्ग मार्ग का निर्माण कार्य कर लिया गया है। उपयुक्तता प्रमाण पत्र प्राप्त आॅन लाईन आपत्तियो का निराकरण कर दिया गया है।दिं0 15.10.2022 को प्रभागीय वनाधिकारी द्वारा भ्रमण किया गया वृक्षो की गणना कर ली गयी है। प्रभागीय वनाधिकारी लैण्ड शड्यूल की कमियों की आपत्तियो मे प्राप्त आपत्तियो का निराकरण कर पुनः प्रेषित। वनभूमि प्रस्ताव प्रभागीय वनाधिकारी स्तर पर विचाराधीन है। -- as on 26-Apr-2024

Rating : 2

Forest Case Pending At : 04: DFO

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: