Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.500 | 0 | 0.000 | 0.000 |
9W341 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1347(1)/।।।(2)/20-58 (एम0एल0ए0)/ 2017 दिं0 24.07.2020
TS Amount (lakhs) : 34.29 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
34.29
Resanction Cost :
34.29
Tentative Cost :
34.29
Exp. Upto Last Fy : 20.38
For CFY 2024-2025
Remaining : 13.91
Demand : 13.88
Allotment : 2.00
Exp in CFY : 1.91
Total Up to Date Exp : 22.28
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 11 months ago
24 Jul 2020
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण माह 05/2021 में पूर्ण। दायित्वो का भुगतान शेष। -- as on 14-Jun-2021
Physical Peramenters