Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 7.22 | 7.22 | 0 |
9W353 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 884/।।।(2)/ 8-52 (एम0एल0ए0)/ 07 दिं0 28.03.2008
TS Amount (lakhs) : 417.47 Lacs
Financial Detail
Sanction Cost : 417.47 Lacs
Resanction Cost : 417.47 Lacs
Exp. Upto Last Fy : 379.38 Lacs
For CFY 2024-2025
Remaining : 38.09 Lacs
Demand : 38.09 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 379.38 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
16 years 1 month ago
28 Mar 2008
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पूर्ण लम्बाई 7.225 किमी0 मे पहाड़ कटान व पार्ट-।। का कार्य पूर्ण। अवशेष पार्ट-।। का कार्य प्रगति पर -- as on 01-Nov-2023
Physical Peramenters