Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 7.22 | 7.225 | -0.0049999999999999 | 0.000 | 0.000 |
9W353 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 884/।।।(2)/ 8-52 (एम0एल0ए0)/ 07 दिं0 28.03.2008
TS Amount (lakhs) : 417.47 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
417.47
Resanction Cost :
417.47
Tentative Cost :
417.47
Exp. Upto Last Fy : 379.38
For CFY 2024-2025
Remaining : 38.09
Demand : 38.09
Allotment : 10.00
Exp in CFY : 8.66
Total Up to Date Exp : 388.04
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
16 years 3 months ago
28 Mar 2008
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मूल प्रस्तावित कार्य पूर्ण कर लिया गया है। कार्य मे हो रही बचत से अन्य अतिआवश्यकत कार्य गतिमान है जो माह 11/2024 तक पूर्ण कर लिया जायेगा। -- as on 03-Jul-2024
Physical Peramenters