Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 2.000 | 2 | 0.000 | 0.000 |
9W356 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 3206/।।। (2) /21-58 (एम0एल0ए0) 2017 टी0सी0-1 दिं0 27.08.2021
TS Amount (lakhs) : 55.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
55.41
Resanction Cost :
55.41
Tentative Cost :
55.41
Exp. Upto Last Fy : 47.17
For CFY 2024-2025
Remaining : 8.24
Demand : 8.23
Allotment : 5.00
Exp in CFY : 6.66
Total Up to Date Exp : 53.83
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
27 Aug 2021
Tentative Completion date:
1 year 6 months ago
31 Dec 2022
Actual Completion Date:
10 months 2 weeks ago
31 Aug 2023
Remark
Bottelneck: no issue
पी0सी0 कार्य पूर्ण दायित्व शेष। -- as on 04-Sep-2023
Physical Peramenters