Work Profile Report [9W381]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E File No 47049 Lok Nirman Anubagh - 2 dt. 16-02-2023
TS Amount (lakhs) : 2.79 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2.79
Resanction Cost :
2.79
Tentative Cost :
2.79
Exp. Upto Last Fy :
6.32
For CFY 2025-2026
Remaining :
-3.53
Demand :
0.63
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
6.32
Work completed
Sanction on : 2 years 10 months ago
16 Feb 2023
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
100 %
Tentative Completion date on : 1 year 8 months ago
04 May 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रथम चरण हेतु कार्य पूर्ण। -- as on 30-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: