Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.75 | 7.75 | 0.000 | 7.75 | 7.750 | 0.000 |
9W389 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1450/।।। (2) 23-03 (सामान्य) 2023 लो0नि0 अनु0- 2 दिं0 02.05.2023
TS Amount (lakhs) : 230.5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
230.50
Resanction Cost :
230.50
Tentative Cost :
230.50
Exp. Upto Last Fy : 115.21
For CFY 2024-2025
Remaining : 115.29
Demand : 115.29
Allotment : 50.00
Exp in CFY : 49.52
Total Up to Date Exp : 164.73
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 80 %
Sanction on :
1 year 2 months ago
02 May 2023
Tentative Completion date:
2 months 3 weeks from now
09 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डामरीकरण, दीवारो का निर्माण का कार्य पूर्ण। नाली सफाई पैरापिट निर्माण कार्य प्रगति पर है। -- as on 18-Jun-2024
Physical Peramenters