Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 7 | 0 |
9W392 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File no 53594 lok niman anubagh 2 dt 18-07-2023
TS Amount (lakhs) : 10.5 Lacs
Financial Detail
Sanction Cost : 10.50 Lacs
Resanction Cost : 10.50 Lacs
Exp. Upto Last Fy : 0.10 Lacs
For CFY 2024-2025
Remaining : 10.40 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.10 Lacs
Technical sanction done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 months 1 day ago
18 Jul 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: Sanction Required form Govt
शा0सं0 ई0फाईल नं0 53594 लो0नि0अनुभाग-2 दिं0 18.07.2023 द्वारा 7.00 किमी0 लम्बाई हेतु रू0 10.50 लाख मात्र की स्वीकृति प्राप्त है। इस स्वीकृति के सापेक्ष विस्तृत सर्वेक्षण कराने के उपरान्त मार्ग के नव निर्माण हेतु मार्ग की वास्तविक लम्बाई 11.00 किमी0 व 60 मी0 स्पान का 1 सेतु की आवश्यकता है जिस हेतु पुनरीक्षित आगणन गठित कर मुख्य अभियन्ता लो0नि0वि0 हल्द्वानी के पत्र सं0 5545/10 याता0-ह0 दिं0 25.11.2023 द्वारा रू0 30.50 लाख का गठित करशासन को स्वीकृति हेतु प्रेषित किया गया है। स्वीकृति आपेक्षित। समरेखन का संयुक्त निरीक्षण राजस्व व वन विभाग के साथ दिं0 28.11.2023 को किया जा चुका है। सी0ए0 भूमि हेतु जिलाधिकारी नैनीताल को पत्र प्रेषित। -- as on 02-Feb-2024
Physical Peramenters