Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.4 | 1.4 | 0.000 | 1.4 | 1.400 | 0.000 |
9W397 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File no 47917 lok niman aubhad 2 dt. 25-09-2023
TS Amount (lakhs) : 53.55 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
53.55
Resanction Cost :
53.55
Tentative Cost :
53.55
Exp. Upto Last Fy : 12.24
For CFY 2024-2025
Remaining : 41.31
Demand : 41.31
Allotment : 40.00
Exp in CFY : 17.77
Total Up to Date Exp : 30.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 95 %
Sanction on :
9 months 3 weeks ago
25 Sep 2023
Tentative Completion date:
4 weeks 18 hours from now
15 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग मे कर्लवट, डामरीकरण व इन्टर लाकिंग का कार्य पूर्ण। नाली एवं पैरापिट निर्माण कार्य प्रगति पर। -- as on 26-Jun-2024
Physical Peramenters