Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.6 | 0.6 | 0.000 | 0.6 | 0.600 | 0.000 |
9W398 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : e- File no 47917 lok niman aubhag 2 dt- 25-09-2023
TS Amount (lakhs) : 53.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
53.91
Resanction Cost :
53.91
Tentative Cost :
53.91
Exp. Upto Last Fy : 34.46
For CFY 2024-2025
Remaining : 19.45
Demand : 19.45
Allotment : 15.00
Exp in CFY : 0.00
Total Up to Date Exp : 34.46
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 95 %
Sanction on :
9 months 3 weeks ago
25 Sep 2023
Tentative Completion date:
2 days 5 hours ago
15 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 02-Feb-2024
Physical Peramenters